After a 26-year journey fraught with formidable obstacles, the 51.38-km Bairabi-Sairang railway line has finally connected Mizoram’s capital, Aizawl, to India’s national rail network. Commissioned in June 2025 by the Commissioner of Railway Safety, this monumental project awaits its grand inauguration by Prime Minister Narendra Modi, marking a new era for the northeastern state.
First envisioned in September 1999, the project faced immediate hurdles. Dense forests, poor visibility, and local resistance rendered a Preliminary Engineering cum-Traffic (PET) survey unfeasible. Instead, a Reconnaissance Engineering-Cum-Traffic (RET) survey was approved in July 2003, completed by Northeast Frontier Railway (NFR) in March 2006. RITES followed with a pre-construction survey in 2008, submitting its final report in August 2011.
Declared a “National Project” in 2008-09 by the UPA government, the project gained momentum when PM Modi laid its foundation stone on November 29, 2014. Land acquisition was completed by 2015, and construction began in earnest. However, the region’s unique challenges tested the resolve of engineers. “The working season is limited to four to five months due to heavy monsoons from April to October,” said Vinod Kumar, Chief Engineer of the project. “Hilly terrain, deep valleys, and frequent landslides made construction exceptionally difficult.”
Also Read: Mizo Students Rally in Aizawl, Demand Dismissal of Unqualified College Teachers
The project’s rugged landscape demanded innovative solutions. With 48 tunnels spanning 12.853 km, 55 major bridges, 87 minor bridges, five road overbridges, and nine road underbridges, the line is an engineering marvel. Bridge No. 196, standing at 104 meters—42 meters taller than Delhi’s Qutub Minar—epitomizes the scale of this achievement. Transporting materials was another hurdle, as narrow, landslide-prone access roads prevented the use of large trucks. Heavy machinery, like cranes, had to be dismantled, transported, and reassembled on-site.
Compounding these issues, Mizoram’s remote location meant scarce local labor and materials. Workers were brought from states like Assam and West Bengal, while construction materials were sourced externally due to local unavailability. “No mobile networks in most project sites added to the isolation, deterring laborers,” Kumar noted. Despite these setbacks, NFR’s relentless efforts ensured 93% completion by July 2024, culminating in full commissioning in June 2025.
The line, featuring four new stations—Hortoki, Kawnpui, Mualkhang, and Sairang—promises to slash travel times, with Silchar to Aizawl reduced from eight hours by road to three by train, and Guwahati to Aizawl from 14-18 hours to about 12. This connectivity is set to boost tourism, trade, and economic growth, aligning with India’s Act East Policy to enhance regional integration.